Earned-value questions on the GTU Project Management paper (3162510) often end with "estimate the cost at completion". There is not a single official EAC. Two common exam methods start from the same PV, EV, AC and BAC and then disagree, sometimes by a lakh or more. If you do not name the assumption, a correct line of arithmetic can still look like a guess.
Cost and earned value (EV, PV, AC, CPI, SPI) is marked High priority on the subject page. That label is guidance, not official mark weight. I work on GTU Hero, and the Project Management page currently lists 5 papers for 3162510, typically 70 marks: Summer 2024, Summer 2023, Winter 2023, Summer 2022 and Winter 2022. No 2025 or 2026 session is on that list. The numbers below are a practice set I computed and checked, not a copy of one of those five papers.
Read the four inputs before any formula
- PV is the planned value: what you planned to have earned by now.
- EV is the earned value: the budgeted value of the work actually done.
- AC is the actual cost: what you have spent.
- BAC is the budget at completion: the original total budget.
EV, PV, AC mix mat karna. A table with the four names and the four numbers at the top of the answer prevents most sign errors.
Worked example
At a review date:
- PV = 6,00,000
- EV = 4,50,000
- AC = 5,40,000
- BAC = 12,00,000
Cost variance CV = EV - AC = 4,50,000 - 5,40,000 = -90,000. Over budget.
Schedule variance SV = EV - PV = 4,50,000 - 6,00,000 = -1,50,000. Behind schedule.
CV uses AC. SV uses PV. Write the words after the signs.
CPI = EV / AC = 4,50,000 / 5,40,000 = 0.833.
SPI = EV / PV = 4,50,000 / 6,00,000 = 0.750.
Both are below 1, which agrees with the negative variances. SPI is weaker than CPI here: the project is in more trouble on schedule than on cost, even though cost is also unfavourable. That sentence is worth putting in the answer. The indices are not just decimals to box.
Two EAC forecasts, written as two assumptions
Method 1. If the current CPI continues, EAC = BAC / CPI.
EAC = 12,00,000 / 0.833 = 14,40,000.
Exactly, 12,00,000 x 5,40,000 / 4,50,000 = 14,40,000. No rounding needed in this set.
Then ETC = EAC - AC = 14,40,000 - 5,40,000 = 9,00,000, and VAC = BAC - EAC = 12,00,000 - 14,40,000 = -2,40,000. The CPI method is forecasting a 2,40,000 overrun.
Method 2. If the remaining work is done at the planned (budgeted) rate, EAC = AC + (BAC - EV).
Remaining budgeted work = BAC - EV = 12,00,000 - 4,50,000 = 7,50,000.
EAC = 5,40,000 + 7,50,000 = 12,90,000.
Same data, two forecasts: 14,40,000 versus 12,90,000. The gap is 1,50,000, and it is not an arithmetic fight. Method 1 believes today's poor cost efficiency continues on the work that is left. Method 2 believes the remaining work can still be done at the original budgeted rate. If the question does not specify, compute both, label both, and say which assumption each one uses.
TCPI: how hard the rest of the work has to be
TCPI to finish on the original BAC is (BAC - EV) / (BAC - AC) = 7,50,000 / (12,00,000 - 5,40,000) = 7,50,000 / 6,60,000 = 1.136.
A value above 1 means the remaining work must be done more efficiently than the original plan, just to land on BAC. Here 1.136, together with a CPI that is already 0.833, is a warning, not a motivational slogan. If a question asks whether finishing on BAC looks realistic, this is the number to point at.
A quick self-check: when PV = EV = AC, CPI = SPI = TCPI = 1, and both EAC methods return BAC. If your formulae do not do that on a simple test row, fix the formulae before the exam, not during it.
Use all five papers, not only the numerical
Recent 3162510 papers are typically 70-mark theory exams. Life cycle, WBS, CPM/PERT scheduling and risk are also High on the subject page. An earned-value sum will not rescue a blank network diagram.
Start with Summer 2024 and the 2023 pair on the GTU Project Management papers page, then the 2022 sessions. When an EAC is asked, write the assumption in the same line as the number. That one clause is the difference between two defensible answers and one unmarked figure.