To charge for extra revisions, settle three things before the project starts: what one revision round is, how many rounds are included, and the price of each extra round, either hourly or as a flat fee. When round three arrives, reply with the price and wait for a yes before you start.
Most revision arguments aren't really about money. They're about what the word "revision" means, so define it first.
Why "one more round" is hard to refuse
Revisions are the most common form of scope creep for designers, developers and content teams, and the hardest to push back on. The client isn't asking for new work. They're asking you to make the existing work right.
So the rounds stack up. Round four is "small tweaks". Round five is "one last thing". Round six undoes something from round two. None of it is billed, the timeline slips, and your effective rate drops.
Being rigid isn't the fix. Writing the rules down before anyone is emotional about the work is.
The definition: what counts as one round
A revision round is one consolidated set of feedback on a deliverable, sent at one time, which you then address in one pass.
Each part of that sentence has a job:
| Part | What it means in practice |
|---|---|
| Consolidated | Feedback from every stakeholder arrives in one doc or message. Five emails on Tuesday are one round only if the client says "that's everything". |
| One deliverable | Homepage feedback is a round for the homepage. It doesn't also cover the About page. |
| Changes, not new direction | Copy edits, colour tweaks, layout shifts and image swaps are revisions. A new direction, page or feature is new work and needs a change request. |
Two edge cases worth putting in writing:
- Your own mistakes don't count. Typos you introduced, broken links and bugs are yours to fix, and they shouldn't use up the client's rounds. Saying so builds trust.
- After sign-off, it's rework. Once a deliverable is approved, reopening it is a change and gets priced like one.
How many rounds to include
There's no universal number. A practical starting point:
| Work type | Included rounds | Reason |
|---|---|---|
| Design and web (common default) | 2 | One round to react, one to refine |
| Logos and brand identity | 3 | Round one is partly about discovering taste |
| Templated or low-ticket work | 1 | The price assumes speed |
Whatever you choose, build it into the base fee. If most clients end up needing three rounds, either include three and raise the fee, or improve the briefing so round one lands closer.
This is normal in design contracts. AIGA's guide to writing design proposals recommends spelling out how many revisions or refinements each phase includes.
Two ways to price extra rounds
hourly: extra_round_cost = hours_spent * hourly_rate
flat: extra_round_cost = fixed_amount per round, per deliverable
setting the flat fee:
flat_fee ≈ average_hours_per_round * hourly_rate
(round it up a little to cover switching back into the project)
| Hourly | Flat fee per round | |
|---|---|---|
| Fits | Dev work and complex pages, where a round can take 20 minutes or a day | Design, copy and video edits, where rounds are fairly consistent |
| Upside | Fair to both sides; small tweaks stay cheap | Easy to understand and approve |
| Downside | The client doesn't know the price upfront | One huge round can eat your margin |
| Fix | Estimate first: "about 2 hours, so about $X" | Cap it: "up to X changes or X hours per round" |
Worked examples (hypothetical: the numbers show the method, not market rates)
A) Hourly
Developer at $90/h, 2 rounds included per page.
Round 3 arrives on the pricing page, estimated at 1.5 h.
1.5 * $90 = $135, quoted before starting.
B) Flat fee
Studio's typical landing-page round takes about 3 h, rate $70/h.
3 * $70 = $210 -> rounded to $225 per extra round, capped at 4 h.
Bigger rounds get a separate quote.
C) What unbilled rounds add up to
Same studio, 10 landing pages a year,
each going 2 rounds past the limit without billing.
10 * 2 * $225 = $4,500 a year of free revision work.
A clause you can adapt
Replace the bracketed parts, and have it checked if a lawyer normally reviews your contracts.
Revisions. The fee includes [two (2)] rounds of revisions per deliverable. A
revision round is one consolidated set of written feedback on a deliverable,
provided at one time, which [Agency/Freelancer] will address in a single pass.
Feedback provided after a round has been delivered starts a new round.
Revisions are adjustments to the agreed concept and scope. New pages, features,
deliverables, or a change in direction are not revisions and will be quoted
separately as a change request.
Additional revision rounds are charged at [$___ per round, per deliverable,
covering up to ___ hours of work] / [$___ per hour]. [Agency/Freelancer] will
confirm the price and any effect on the timeline before starting, and work on
additional rounds begins only after the Client approves in writing (email is
sufficient).
Changes to a deliverable after the Client has approved it are treated as
additional work. Corrections of errors made by [Agency/Freelancer] do not count
as a revision round.
The line that matters most is in the third paragraph: the price is confirmed and approved before work starts, so a revision fee never shows up as a surprise invoice. The AIGA Standard Form of Agreement works the same way: client changes outside the agreed scope are billed on top of the fee and documented with a change order the client signs.
Three replies for when the rounds run out
Round three arrives
Thanks for the notes, all clear. Quick heads-up: this will be round 3, and your
plan includes 2 rounds per page, so this one is an extra round at [$___]. It'd
add [about a day] to the timeline. Reply "go ahead" and I'll start today.
It names the policy without lecturing, and it gives the price, the timeline and one easy next step. It only works if you've kept count from the first delivery.
"Why am I being charged for revisions?"
Fair question. Your quote included 2 rounds per deliverable, and that's what the
price was based on. Extra rounds take the same time as the first two, so they're
priced separately at [$___]. If you'd rather not go over, I'm happy to help you
combine everything into one final list so we get it right in this round.
It points back to what was agreed and offers a free way to stay in budget.
"Just this once?"
I get it. I'd rather keep the rate consistent so it stays fair across all my
clients, but here's what I can do: if you send all remaining changes in one
list, I'll treat them as a single round at [$___], even if there are a few.
Want to go that way?
It holds the price but gives the client some control, and one bundled round is less work for you than drip-fed edits.
Habits that keep the policy working
- Count rounds out loud: "Here's round 1 of 2" in the delivery message.
- Ask for consolidated feedback: one doc, one deadline, every stakeholder.
- Answer extra-round requests the same day, with price and timeline.
- Log approved extra rounds per client. At renewal, the log shows whether the package needs more rounds or a higher price.
Originally published at creepless.online. This version was drafted with AI assistance.
Top comments (10)
The consolidated-feedback rule is the part I wish I had learned earlier. I used to get five separate messages from different stakeholders and treat each one as its own round, which meant the work never really ended. Naming the round out loud in the delivery message — "here is round 1 of 2" — also changes the dynamic: the client starts grouping their own notes instead of sending them one at a time. One question: when a client sends a genuinely small extra note after the two rounds, do you still charge the full flat fee, or do you have a smaller minor-tweaks tier for those?
Good question. A full flat fee for a one-line tweak feels heavy-handed, so a small "minor tweaks" tier (or a short hourly cap agreed in advance) works well for those. What matters is that the tier is written down before round three, so the client knows what a "small note" costs before they send it.
That's the part I'll keep — the tier has to exist before round three, not after the awkward email. A small tweaks tier keeps the one-line fix from feeling like a punishment, and the client already knows what a 'small note' costs before they send it. Really appreciate you spelling out the timing, not just the price.
Agreed, the timing is the whole trick. Once the price is known before the request, the client can decide for themselves whether a note is worth sending now or saving for the next round. Thanks for the back-and-forth.
Exactly — knowing the price before the request is what makes it the client's call, not a negotiation. If it's worth it now, they send it; if not, it waits for the next round without any awkwardness. Thanks for the back-and-forth.
Right, and it keeps things friendly because nobody has to argue about it in the moment. Appreciate you taking the time to think it through here.
The definition does the heavy lifting here — "one consolidated set of feedback, sent at one time" is the sentence I'd copy into any contract. The edge case I'd worry about: one stakeholder replies late, after the others already sent their doc. Does the round clock start when the first feedback lands, or only once the consolidated doc is complete? That gap is where I've seen rounds quietly multiply.
That gap is exactly where rounds multiply. The cleanest fix is to start the round only when the consolidated doc arrives, and to name one person on the client side who sends it. Late notes from another stakeholder then go into the next round instead of reopening the current one.
Defining a revision round as one consolidated set of feedback on one deliverable is a really clean rule. In my experience, putting that in writing before kickoff saves a lot of awkward conversations later.
Agreed. Putting it in writing before kickoff turns a later awkward conversation into a quick "per our agreement" reply. Thanks for reading.