Mold cost tiers: multi-cavity steel loses 3-8 RMB/part under 50k units

Mold cost for an enclosure splits into three tiers, and choosing the wrong tier is not a one-off expense. It is a per-unit tax that follows the product for its whole life.

The soft tier, aluminium or resin tooling, runs 8,000 to 25,000 yuan and lasts 5,000 to 30,000 shots. Its life and accuracy ceiling are both low. Resin tooling starts wearing after 3,000 to 5,000 shots, and textured parts sooner. Aluminium reaches 30,000 to 50,000 shots, but sliding cores and lifters wear faster than steel, so batch consistency fails before the tool does.

The right way to use a soft tool is validation plus first launch: shoot T0 parts to check assembly, put three to five thousand units on the market, and cut the steel tool in parallel. Running a soft tool as if it were production tooling shows up around shot twenty thousand, when flash grows thick enough that the assembly station starts hand-trimming every part.

Single-cavity steel

Three to eighty thousand yuan, thirty-thousand-plus shots. This is the mainstream band for five thousand to fifty thousand units a year, and it is where most products should live.

The quoted price varies by a factor of two for the same nominal specification. The difference sits in four places: steel grade (P20 versus 718H, roughly thirty percent), mold base class, hot runner type (valve gate versus open, 8,000 to 20,000), and the least visible item of all, whether the tool shop includes a trial run and on-site support. Trial runs cost 1,500 to 3,000 per machine day plus a setup technician plus rework. A quote that lists trials separately looks cheaper and finishes more expensive.

Multi-cavity, and the cost people forget

A two-cavity tool is not simply two parts per cycle. Projected area doubles, so the machine goes up a size class (168 to 268 tonnes) and machine rates rise 35 to 50 percent. Cycle time grows 10 to 20 percent because of shot size and cooling. A part that cycles in 38 seconds single-cavity commonly runs 46 to 50 seconds two-cavity.

So the real multi-cavity arithmetic trades higher machine rate and longer cycle against reduced labour and mold amortisation. Above two hundred thousand units a year it wins clearly. Around one hundred thousand it has to be computed part by part, and between those two figures there is almost always a middle option worth tabulating: single cavity plus semi-automation.