Five Directors Priced an Hour of Downtime and Together It Came to Three Times Our Turnover

Last winter I was asked to make the case for a second network core, so that a failure at head office would no longer stop the depots. The board wanted to know what an hour without our systems costs, and I did what most of us do. I asked each director.

Sales said forty eight thousand pounds an hour in lost orders. Transport said thirty five thousand in missed deliveries and customer penalties. Finance said twenty two thousand, from invoices not raised and cash arriving late. Operations said nine thousand in idle warehouse labour, and customer services added overtime. The total was a little over a hundred and twenty thousand pounds an hour.

The finance director read it and pointed out that we turn over about forty five thousand pounds an hour, averaged across the year. My paper was telling the board that an outage loses nearly three times what we take. The case was deferred, and I lost some credibility that day.

Every director had been honest. Each had counted the same orders from their own side. The order that was not taken is the delivery that was not made and the invoice that was not raised, and it had been counted three times. And most of it was not lost at all. When we looked at our two real outages from the previous year, about eighty five percent of the orders that should have arrived during them arrived later the same day. Customers waited, then ordered.

So we rebuilt the estimate by following the money rather than the departments. The margin on orders that never came back. Penalties actually paid under our contracts. Overtime actually worked. Labour that was paid for and not recovered later in the shift. On an ordinary day it came to about eleven thousand pounds an hour, and more in the weeks before Christmas.

The smaller number was approved at the next meeting, because every line of it could be checked against something that had happened. The investment paid for itself on that estimate, and it had never needed the bigger one to do so.

When each department prices a problem from where it sits, the same pound gets counted at every desk it passes. Count it once, at the point it actually leaves the company.

– Serguey Shinder